Design and Build Warehousing and Distribution Unit Incorporating Two Storey Office Block.

P.K.Construction Ltd. acted as Principle Contractor and CDM Co-ordinator on this project. This included the development of a Construction Phase Plan and Health & Safety file together with all information and documentation required under the then active CDM Regulations (2007) for the roles of Principal Contractor, Co-ordinator and Designer.

P.K.Construction Ltd. undertook this full turnkey package including land acquisition and planning application. The project encompassed a 40,000sqft transport warehouse and 5,000sqft of offices and 2 acres of trailer parking.

The project comprised; piling (pre-cast driven), pile caps and ground beams, pre-cast slabs to office floors. Masonry, structural steelwork (DES), cladding, foul water and storm water drainage, steel fibre reinforced warehouse slab, tarmac surfacing to trailer parking. General building works to offices including interior finish. Site perimeter fencing and landscaping.