Colt: Network Rail Maintenance Depots – Finsbury and Cricklewood
Civils Contractor for the civils element of the Maintenance Depots at Cricklewood and Network Rail. Cricklewood involved the excavation and construction of a Reinforced concrete raft foundation and 1300m2 of concrete hard standing.
Finsbury Park works involved 44No. augured concrete piles to support a beam foundation of a Portakabin modular building. There was 1000m2 of concrete hard standing, 1000m2 of Tarmac and 440m2 of permeable block paving.
P.K. Supplied: Site Manager, Engineer, Site Supervisor, Ground Workers, Machine Drivers, Joiners, Steel Fixers
P.K. Sub-Contractors: Steel Fixers, Auger Pilers, Brick layers